Project Description

The Brief

Dilapidations of the former BHS store in Brighton Churchill Square ready to be converted for the new occupier, Zara.

The Works

Pristine London were appointed as principal contractor to undertake a full strip out, including the removal of escalators, a roof plant, and all asbestos through out.

Pristine also undertook the Builders Works package this included a substantial amount of block work to divide areas and create breakout space. Other builders work included screeding through out, installing fire rated hoarding, and carrying out M&E Isolations throughout.

Due to the nature of the project, the team here had to communicate closely with the shopping centre management. A lot of the works need to be completed out of hours, with a high amount or noise and dust control, ensuring we did affect any other demises in the Shopping centre.

Pristine London has received some fantastic feedback from this project. It has led to another 3 projects with the team.